A lot has happened in the past two weeks:

  • Tees 13, 5, 11, 18 have been seeded
  • Bunkers on 11 fairway are nearly complete; 5 fairway will be finished by next week
  • OHCC staff has been expanding fairways using aerification plugs
  • 15 fairway has germinated
  • The seawall at the new pond is complete; finish work begins today
  • Cart paths on 15 & 16 are complete
  • 1/10 tees will be sodded next Tuesday
Our staff has been working late into the evening to complete our portion of the work. They deserve a big thank you for making the necessary sacrifices. John and Stephen have been left alone on the South Course to keep our Championship 18 in great condition.

I would anticipate a mid-May opening for the North Course in 2014.