North Reno Update

We continue to make good progress with this exceptional weather helping us along.

The PG was seeded on August 20th.
Cart path installation around the PG and first tee is complete.

This week:
Finish grade on 12, 13, 15, and 17 tee complexes.
Complete final tree work.
Irrigate holes 15 and 13.
Finish step 1 of new seawall.

Next week:
Cart path around hole 13 - about 1,000 feet of 10 ft wide path.
Seed 12,13,15,17 tees and 15 fairway.
Continue seawall work.



Removal of Spruce bottom #1 frwy


PG after sodding/cart path work